| Key Concept and Formulas for PMP Exam | |
| Earn Value Formulas | Project Selection Financials |
| PV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled EV (Earned Value) = BCWP (Budgeted Cost of Work Performed) AC (Actual Cost) = ACWP (Actual Cost of Work Performed) SV = EV – PV (minus is behind schedule) CV = EV – AC (minus is over budget) SPI = EV/PV (Less than 1 is behind schedule) CPI = EV/AC (Less than 1 is over budget) EAC = AC + (BAC-EV) Use when variances are atypical EAC = AC + [(BAC-EV)/CPI] Use when variances are typical (Note: This is the same as EAC = BAC/CPI) VAC = BAC – EAC ETC = BAC – EV Use when variances are atypical ETC = (BAC – EV)/CPI Use when variances are typical ETC = EAC – AC Use when original estimates were flawed | NPV (Net Present Value) = FV/(1+r)n FV= Future Value, r= interest rate, n= no. of time periods Higher NPV is better IRR (Internal Rate of Return) = Solve the NPV equation for “r” Also called Hurdle Rate Higher IRR percentage is better BCR (Benefit/Cost Ratio) Higher BCR is better. Beware, exam can call it CBR, where lower is better ROI (Return on Investment) = Earnings/Investment Higher ROI is better Payback Period = Time to recover cost of the project Lower payback period is better Cash Flow = Cash In – Cash Out |
| Network Diagram | Calculating Stackor Float |
| Precedence Diagramming Method (PDM)
Arrow Diagramming Method (ADM)
Graphical Evaluation and Review Technique (GERT)
| Total Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed without delaying the project finish date. Free Float/Slack is the amount of time an activity can be delayed without delaying its successor (following activity).
Lag Time: Inserted wait time between activities Lead Time: Overlapping activities, also called paralleling or fast tracking. “Lead In; Lag Out” |
| Three Point Estimates, or PERT | Accuracy of Estimates |
| PERT = PROGRAM Evaluation and Review Technique Holds schedule and lets cost float 3 estimates for each task: Optimistic, Pessimistic, and Most Likely Mean Estimate = (O + 4*ML + P)/6 Standard Deviation (s) = (P – O)/6 Variance = s2 , or [(P – O)/6]2 Standard deviation of tasks on CP = Sum of variances | Order of Magnitude:-25% to +75% Budget Estimate:-10% to +25% Definitive Estimate:-5% to +10% |
| Powers of a Project Manager | Conflict Resolution (Best to Worst) |
| 1. Expert: Best, earned on your own 2. Reward: Next best. Based on PM position 3. Formal: Power, based on PM position 4. Referent: Referring to positions of others 5. Penalty: Worst. Based on PM position | 1.Problem Solving: Also called Confronting 2. Compromising: Solutions satisfy both parties 3. Withdrawal: Postponing a decision 4. Smoothing: Emphasis on agreement 5. Forcing: One viewpoint at expense of another. |
| Sources of Conflict (Order of Priority) | Herzberg’s Motivators |
| 1. Schedules 2. Project Priorities 3. Resources 4. Technical Opinions 5. Administrative Procedures 6. Cost 7. Personality | 1. Achievement 2. Recognition 3. Challenge of the work itself 4. Responsibility 5. Advancement 6. Growth |
| Channels of Communication | Closing |
| Between Team Members = N(N-1)/2 | Project is closed when administrative closure is complete. Administrative closure is done at end of each Project Phase and at the end of the Project. Contract closure: verification that deliverables were acceptable; it is done once at the end of the contract. Contract Closure Procedure is produced under “Close Project” |
Hiç yorum yok:
Yorum Gönder