Key Concept and Formulas for PMP Exam

Earn Value Formulas

Project Selection Financials

PV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled

EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)

AC (Actual Cost) = ACWP (Actual Cost of Work Performed)

SV = EV – PV (minus is behind schedule)

CV = EV – AC (minus is over budget)

SPI = EV/PV (Less than 1 is behind schedule)

CPI = EV/AC (Less than 1 is over budget)

EAC = AC + (BAC-EV) Use when variances are atypical

EAC = AC + [(BAC-EV)/CPI] Use when variances are typical

(Note: This is the same as EAC = BAC/CPI)

VAC = BAC – EAC

ETC = BAC – EV Use when variances are atypical

ETC = (BAC – EV)/CPI Use when variances are typical

ETC = EAC – AC Use when original estimates were flawed

NPV (Net Present Value) = FV/(1+r)n

FV= Future Value, r= interest rate, n= no. of time periods

Higher NPV is better

IRR (Internal Rate of Return) = Solve the NPV equation for r

Also called Hurdle Rate

Higher IRR percentage is better

BCR (Benefit/Cost Ratio)

Higher BCR is better.

Beware, exam can call it CBR, where lower is better

ROI (Return on Investment) = Earnings/Investment

Higher ROI is better

Payback Period = Time to recover cost of the project

Lower payback period is better

Cash Flow = Cash In Cash Out

Network Diagram

Calculating Stackor Float

Precedence Diagramming Method (PDM)

  • Also called Activity on Node (AON): Activities are in boxes
  • Most commonly used today
  • Has 4 relationships: F-S, S-S, F-F, S-F
  • No “dummies” (zero duration dependencies) allowed
  • Can analyze using either Three-Point Estimates or CPM

Arrow Diagramming Method (ADM)

  • Also called Activity on Arrow (AOA)
  • Only 1 relationship: F-S
  • Can have “dummies”
  • Can analyze using either Three-Point Estimates or CPM

Graphical Evaluation and Review Technique (GERT)

  • Allows loops and repetitive activities

Total Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed without delaying the project finish date.

Free Float/Slack is the amount of time an activity can be delayed without delaying its successor (following activity).

  • LS – ES: Calculates slack with forward pass
  • LF – EF: Calculates slack with backwards pass

Lag Time: Inserted wait time between activities

Lead Time: Overlapping activities, also called paralleling or fast tracking.

“Lead In; Lag Out”

Three Point Estimates, or PERT

Accuracy of Estimates

PERT = PROGRAM Evaluation and Review Technique

Holds schedule and lets cost float

3 estimates for each task: Optimistic, Pessimistic, and Most Likely

Mean Estimate = (O + 4*ML + P)/6

Standard Deviation (s) = (P O)/6

Variance = s2 , or [(P – O)/6]2

Standard deviation of tasks on CP = Sum of variances

Order of Magnitude:-25% to +75%

Budget Estimate:-10% to +25%

Definitive Estimate:-5% to +10%

Powers of a Project Manager

Conflict Resolution (Best to Worst)

1. Expert: Best, earned on your own

2. Reward: Next best. Based on PM position

3. Formal: Power, based on PM position

4. Referent: Referring to positions of others

5. Penalty: Worst. Based on PM position

1.Problem Solving: Also called Confronting

2. Compromising: Solutions satisfy both parties

3. Withdrawal: Postponing a decision

4. Smoothing: Emphasis on agreement

5. Forcing: One viewpoint at expense of another.

Sources of Conflict (Order of Priority)

Herzberg’s Motivators

1. Schedules

2. Project Priorities

3. Resources

4. Technical Opinions

5. Administrative Procedures

6. Cost

7. Personality

1. Achievement

2. Recognition

3. Challenge of the work itself

4. Responsibility

5. Advancement

6. Growth

Channels of Communication

Closing

Between Team Members = N(N-1)/2

Project is closed when administrative closure is complete.

Administrative closure is done at end of each Project Phase and at the end of the Project.

Contract closure: verification that deliverables were acceptable; it is done once at the end of the contract.

Contract Closure Procedure is produced under “Close Project”